Campus Center Timeline Announced
Student Life and Diversity has released an updated timetable for the opening of the Campus Center.
The current schedule is as follows:
- Anticipated substantial construction on the Campus Center completed – Oct. 1, 2007.
- Move-in of furnishings, fixtures and equipment completed – October and November 2007.
- Department move-ins completed – Beginning in Nov. 2007.
- Soft Opening of the Campus Center – Dec. 1, 2007.
Dates are subject to change.